Field Notes · 2026-05-19
Preparing visuals for a lender site update in Vietnam
A calm checklist for packaging progress, cost, and contractor status before a financing review.
Lenders rarely want every drawing. They want proof that milestones claimed in the last draw still hold, and that cost movement has an explanation.
Assemble three panels: progress against programme, variance by major package, and open contractor blockers. Keep supporting ledgers in an appendix.
Schedule an Owner Briefing Session a few days before the meeting. Practising answers to ‘why is façade float gone?’ saves awkward pauses in the room.
Use consistent photo angles month to month. Lenders notice when a balcony that looked finished in April looks unfinished in May from a different corner.